PROJECT INFORMATION

Client: Bitdeer Technologies Group and Druk Holding & Investment

Location: Jigmeling, Gelephu, Sarpang 

Year of Completion: 2025 (expected year of completion)

Value: Nu. 2500 million (expected executed amount)

Project Manager: Karma Tshering

Project Description: Vajra Builders Private Limited secured the ongoing project of construction of 500MW substation in 2024. It is a venture between Druk Holding and Investment (DHI) and Bitdeer Technologies Group. The project is scheduled to be completed and commissioned by December 2025. 

The scope of the project includes construction of the following infrastructures:

1. GIS Substation

2. PEB Structures for GIS equipment, office, and staff quarters

3. 1.40 million cubic meters of earth-cutting and levelling

4. RCC equipment foundations and platforms

5. 6.50 km of internal road construction